|
|
|
|
Groundwater
Exploitation in Paros |
The construction of new boreholes to provide additional
water supply is the method that has been used most
frequently in the case of Paros, as until recently the
groundwater reserves were adequate, the costs entailed in
the use of boreholes are significantly lower than those of
major structural solutions, such as reservoir construction
or desalination, and the solution was quick and easy to
implement. As a result, the island today is perforated by a
large number of boreholes, most being used for irrigation
purposes. The size of this potential water management
intervention as a component of the comprehensive scenarios
for Paros was defined in the basis of the local geological
structures and the current exploitation patterns. Since
little or no data are available for abstracted water volumes
from irrigation, the option is examined for domestic use
only. Very low priority is given to the new supply source.
As in the case of Network Unifications, the size of such an
intervention cannot be varied on the basis of demand
conditions, since it depends more on available quantities
for abstraction. Thus it was the schedule of implementation
(see Annex) that was defined by the demand – availability
conditions in the area, and formed the extent for the
application of the option.
The locations that could be selected for the application of
this intervention were:
-
The Agairia – Alyki area. This area does not face
water deficit, and thus can provide water for other
parts of the island. However, this can only be effected
in conjunction with network unifications, as this water
network is currently isolated.
-
The Archilohos area. This area faces small, periodic
deficits, and exhibits low water exploitation. An
additional borehole yielding about 47,000 m3/yr can be
constructed.
-
The Kostos area, in order to supply water to the main
town of Paroikia and its suburbs. A maximum of two new
boreholes can be constructed here, based on current
estimates, yielding about 75,000 m3/yr each.
-
The Glysidia area. However, the local aquifer is
non-productive and vulnerable to salinisation; to that
end, it is estimated that a borehole yielding only 7,000
m3/yr should be constructed.
|
|
|
Option details and results
|
The yields and costs of the proposed interventions are summarized in Table 1.
|
Table 1. Yield and construction costs for new boreholes
Borehole |
Yield (m3/yr) |
Construction Cost (€) |
Arhilohos |
47,000 |
40,000 |
Glysidia |
7,000 |
20,000 |
Kostos 1 |
75,000 |
40,000 |
Kostos 2 |
75,000 |
40,000 |
Total |
204,000 |
140,000 |
Figure 1 presents quantities abstracted from the new drillings for the
BAU+Normal scenario. The month variation of water production for a normal, dry
and wet year (2009 under the three scenarios) is presented in
Figure 2.
Figure 1. Additional Groundwater Abstractions (BAU+Normal scenario)
The new boreholes are assigned a very low supply priority with respect to
existing supply sources. For this reason, under all three scenarios the new
boreholes operate after the peak summer months, when the traditional supply
sources have been depleted. During the peak season, supply normally originates
from the existing groundwater drillings.
Figure 2. Monthly variation of abstractions from the new boreholes (2009)
Top
|
Effectiveness
|
The coverage of Domestic demand shows some improvement where the option is
applied, which is once again diminished as the demand grows over time (Figure
3). Although the traditional practice of groundwater exploitation can
assist in meeting some domestic requirements, this effect is almost diminished
in cases of drought, as it is depicted from the results of the BAU+HD scenario (Figure
4).
Figure 3. Percent demand coverage effectiveness of Groundwater exploitation
to Domestic use
Figure 4. Percent Improvement of deficit in Domestic use with respect to the
reference scenarios
In general, irrigation deficits are not significantly affected, with the
exception of the high dry scenario (Figures
5 and 6).
Figure
5. Percent demand coverage effectiveness of Groundwater exploitation to
Irrigation use
Top
|
Direct and Environmental Costs
|
Overall the
direct cost increases are similar to those of the network unification option. A
small average increase of about 3.5-5% is common among all three scenarios.
Infrastructure construction costs are low; the increase is due to the
augmentation of water abstracted and delivered to domestic use, which incurs a
proportional increase in annual operating costs
Figure 7. Total direct cost difference of the
Groundwater exploitation option under the three scenarios (Present Value – Million €)
The total environmental cost records a substantial increase due to the increase
of groundwater abstractions. In all cases, it is considerably higher than the
respective reference case, with the highest values recorded for the high dry
scenario (Figure 8).
Figure 8.
Total environmental cost difference of the Groundwater exploitation option under the
three scenarios (Present Value – Million €)
Top
|
|
|